A 200-metre turbine between rice fields and wetlands: Albons fights a wind power plan

Albons council, local residents and the campaign group Defensem l’Empordanet have lodged objections to the Molí de Salancs, a 5-megawatt wind turbine that the energy company Estabanell wants to build in a wildlife corridor between the Aiguamolls and Montgrí nature parks in the Baix Empordà. Mayor Josep Ramon Llavero says he will go to court if the Catalan government approves it. The company insists the project is viable and has offered a public meeting in late November.

· · Albons
Share
200 m5 MW
Illustration: The Costa Brava Times

The project

Estabanell, a Catalan electricity distributor, describes the Molí de Salancs as its first wind project in Catalonia. It would be a single turbine 200 metres tall with 5 megawatts of capacity, producing an estimated 13,000 megawatt hours a year, roughly what 4,300 homes use. It would stand in Albons, 1.84 km from one protected area and 1.27 km from another, on a strip of farmland that acts as a corridor for wildlife between the Aiguamolls de l’Empordà wetlands, the Montgrí massif, the Medes Islands and the lower Ter valley.

According to the objections, the turbine would be 181 metres from the Can Lloca farm, 305 metres from Can Turies and 514 metres from the Can Virosquet farmhouse.

Why people object

The council’s submission lists 29 grounds and asks for an unfavourable environmental ruling. The main ones are the impact on the wildlife corridor and on protected birds such as the booted eagle, Montagu’s harrier and black kite, as well as bats; noise for neighbouring farms; the loss of irrigated land that received public money for modernisation; and the lack of geological and groundwater studies. Objectors also say the wind resource was modelled rather than measured on site, and that no public meeting was held before the consultation closed on 6 November.

The mayor says he is not against renewables, only against this project in this place, and points out that the Catalan government rejected four turbines at la Tallada d’Empordà, about four kilometres away, on landscape grounds. “Residents won’t get free electricity,” he says.

The company’s view

Pere Borràs of Estabanell says the distances were chosen with farming and housing in mind and that beyond 500 metres the noise is indistinguishable from background levels. He admits the bird-collision risk is still being studied and that returns could fall in less favourable scenarios. He says the power would be used locally and denies any plans for a data centre. The Catalan government’s departments must now assess the objections and decide whether the project can be modified or should be refused.

The Molí de Salancs

  • One turbine, 200 m tall, 5 MW
  • About 13,000 MWh a year, enough for 4,300 homes
  • 29 objections from the council
  • 181 m from the nearest farm