Catalonia’s new desalination plants at Blanes and Foix delayed to 2031; a Muga plant for the Alt Empordà still under study
The Catalan and Spanish governments have signed the deal to expand the Tordera desalination plant at Blanes, at the southern tip of the Costa Brava, and build a new one at Foix, south of Barcelona: an investment of more than €500m that will more than double desalination capacity from 80 to 170 cubic hectometres a year. Tenders and works start in early 2027, but the plants will not run until 2031. A plant on the river Muga, planned for the Alt Empordà, is still at the stage of studying alternatives.
After the worst drought in living memory in Catalonia, the bet on desalinated water now has a signed agreement, but also a longer timetable than planned. On Tuesday the Catalan government approved its deal with the Spanish state to expand the Tordera plant at Blanes and build a new one at Foix, on the Penedès coast south of Barcelona. The works will be carried out by the state water company Acuamed, with the Catalan Water Agency and the regional supplier Aigües Ter-Llobregat on its decision-making bodies.
The numbers
The investment tops €500m, about €290m of it at Blanes. Together, desalination capacity will rise from 80 to 170 cubic hectometres a year. Tenders and works are due to start in early 2027, but the plants will not come on stream until 2031. According to the news site Nació Digital, the delay is down to red tape and missed deadlines for EU funds, which have forced a new mix of state and market financing. Catalan climate minister Sílvia Paneque calls the plants “absolutely key” for future droughts.
And the Empordà?
For the northern Costa Brava, the key piece is the future desalination plant on the Muga in the Alt Empordà, still at the stage of studying alternatives. The Baix Empordà relies largely on aquifers and the river Ter, and the Catalan government’s goal is for 70% of water to come from sources that do not depend on rain, such as desalination and recycled water, by 2030. Today the Ter-Llobregat reservoirs are 82.6% full, according to the Catalan Water Agency, after a generous autumn, but recent years have shown how quickly a healthy reserve can vanish.
Why it matters
With a warmer climate and more erratic rain, the Ter-Llobregat system, which supplies about 5.5 million people, needs sources that do not depend on the sky. Until 2031, though, any long drought will again mean restrictions and reliance on the plants already running.
The facts
- Investment: over €500m (about €290m at Blanes).
- Capacity: from 80 to 170 hm³ a year.
- Works from 2027; running by 2031.
- Ter-Llobregat reservoirs: 82.6% (Catalan Water Agency, 24 November).
Sources: Nació Digital · Crónica Global · ACA ·