Share

The utility Endesa has invested €500,000 in the first phase of renewing the electricity network in central Figueres, an area full of shops, restaurants and council buildings. It has replaced old switchgear and low-voltage boards with new sealed, safer units, and the substation will soon be remotely controlled from its control centre, which it says can cut the time customers are left without power after a fault by up to 20%. Work began on 19 October, with generators keeping supply going. Seven transformer stations in the town have been refurbished this year, and five more new-line projects from the Carrer Navata substation are being designed.

Source: El Gerió Digital ·